1, have been completed Kyaukpyu first stop, G100 + 500, G100 + 800 , G100 + 850, G100 + 900, G101 + 200, G75 + 950, G114 + 150, G114 + 000, G116 + 000, G118 + 000, G123 + 000, G147 + 000, G147 + 230, G148 + 850 troubleshooting, and water conservation works; <br>2, G110: pouring retaining wall is complete, the site slopes clean-up; supervision visits to check; <br>3, G132 + 200: no construction schedule; <br>4, G132 + 300: the scene of the work already done for maintenance rectification, mainly deal with anti-slide pile below ground subsidence, cracking rows of inverted trough, and planting vegetation to strengthen supervision routine inspection checks. <br>5, each process point to problems found in the inspection, supervision and construction unit as soon as possible. "