1, on-site inspection found that the G100-900 construction section is in a steep section, requiring the construction unit to build temporary side road; (see photo)<br>2, the site supervision inspection process found that the construction unit construction site individual operators did not wear a hard hat, the supervision has verbally informed the construction contractor to immediately rectify, has now completed the rectification. <br>" <br>1, the entry cement requirements under the pad cover;<br>"1, mechanical equipment oil leakage, site supervision requires repair when laying pads (see photo) 2, underground work lighting equipment plug-in board use is not standardized, has been required to carry out rectification (see photo) "