1、监理巡视过程中发现施工单位现场挡墙混凝土浇筑未做及时养护,当场要求立即整改,现已完成整改。2、G75+000管道涵洞盖板钢筋绑扎及模板支的英语翻译

1、监理巡视过程中发现施工单位现场挡墙混凝土浇筑未做及时养护,当场要求

1、监理巡视过程中发现施工单位现场挡墙混凝土浇筑未做及时养护,当场要求立即整改,现已完成整改。2、G75+000管道涵洞盖板钢筋绑扎及模板支护不符合图纸要求,经整改后验收通过; (详见照片)3、G116顶梁下一根钢管桩埋在土内,要求施工单位核对钢管桩数量。(详见照片)" 1、G147+230 排水沟验槽槽底浮土石块未清理干净,现场已经要求进行整改,并整改完成(详见照片) "1、抗滑桩护壁锁口盘底板钢筋绑扎未按图纸要求预留保护层,保护层厚度不符合图纸要求;现场监理要求进行整改,并整改完成(详见照片)2、进场黄砂质量不符合规范及图纸要求,已下发监理通知单,并对同批次黄砂进行退场(详见照片)" 检查材料进场情况。
0/5000
源语言: -
目标语言: -
结果 (英语) 1: [复制]
复制成功!
1, found during the inspection supervision and construction units on-site pouring concrete retaining wall without making timely maintenance, the spot requires immediate rectification, the rectification has been completed. <br>2, G75 + 000 culvert pipe and plate steel binding template does not meet the requirements of the drawings support, after acceptance by rectification; (see photo) <br>3, a lower headpiece G116 steel pipe pile embedded in the ground, require the construction unit check the number of steel pipe piles. (See photo), " <br>1, 230 + G147 drain groove bottom surface dust test stones is not clean, the scene has been requested for rectification, and to complete the rectification (see photo) <br>" 1, Wall Friction Pile locking disc plate steel lashing drawings reservation fails protective layer, the protective layer thickness does not meet the requirements of the drawings; site supervision requirements for rectification, and to complete the rectification (see photo) <br>2, yellow sand entering the quality does not meet specifications and drawings, it has issued a notice supervision single, and conduct exit (see photo) "The same batch of sand- <br><br> <br>checking materials approach the situation.
正在翻译中..
结果 (英语) 2:[复制]
复制成功!
1, supervision and inspection process found that the construction unit site retaining wall concrete pouring did not do timely maintenance, on the spot requirements for immediate rectification, has now completed rectification.<br>2, G75-000 pipe culvert cover steel strapping and template support does not meet the requirements of the drawings, after rectification acceptance passed; (see photo for details) 3, G116 under the top beam of a steel pipe pile buried in the soil, the construction unit is required to check the number of steel pipe piles. <br>(see photo) <br>1, G147 and 230 drainage ditch trench bottom floating earth stone has not been cleaned up, the scene has been required to carry out rectification, and rectification completed (see photo)<br>"1, anti-slip pile wall lock plate bottom plate steel tied not in accordance with the drawing requirements reserved protection layer, the thickness of the protective layer does not meet the requirements of the drawing; <br><br>2, entering the yellow sand quality does not meet the specifications and drawing requirements, has issued a supervision notice, and the same batch of yellow sand exit (see photo) " Check the entry of materials.
正在翻译中..
结果 (英语) 3:[复制]
复制成功!
1. In the process of supervision and inspection, it was found that the retaining wall concrete pouring of the construction company was not cured in time, and rectification was required immediately on the spot, which has been completed.<br>2. G75 + 000 pipe culvert cover plate reinforcement binding and formwork support do not meet the requirements of the drawings, and pass the acceptance after rectification; (see photo for details)<br>3. A steel pipe pile under G116 top beam is buried in the soil, and the construction company is required to check the number of steel pipe piles. (see photo for details)“<br>1. The floating soil and stones at the bottom of G147 + 230 drainage ditch inspection groove have not been cleaned up. Rectification has been required on site and completed (see photo for details).<br>"1. The anti slide pile wall lock plate bottom plate reinforcement binding did not reserve the protective layer according to the requirements of the drawings, and the thickness of the protective layer did not meet the requirements of the drawings; the site supervision required rectification and rectification was completed (see the photo for details).<br>2. If the quality of yellow sand entering the site does not meet the requirements of specifications and drawings, a supervision notice has been issued and the same batch of yellow sand has been removed (see the photo for details).“<br>Check the mobilization of materials.<br>
正在翻译中..
 
其它语言
本翻译工具支持: 世界语, 丹麦语, 乌克兰语, 乌兹别克语, 乌尔都语, 亚美尼亚语, 伊博语, 俄语, 保加利亚语, 信德语, 修纳语, 僧伽罗语, 克林贡语, 克罗地亚语, 冰岛语, 加利西亚语, 加泰罗尼亚语, 匈牙利语, 南非祖鲁语, 南非科萨语, 卡纳达语, 卢旺达语, 卢森堡语, 印地语, 印尼巽他语, 印尼爪哇语, 印尼语, 古吉拉特语, 吉尔吉斯语, 哈萨克语, 土库曼语, 土耳其语, 塔吉克语, 塞尔维亚语, 塞索托语, 夏威夷语, 奥利亚语, 威尔士语, 孟加拉语, 宿务语, 尼泊尔语, 巴斯克语, 布尔语(南非荷兰语), 希伯来语, 希腊语, 库尔德语, 弗里西语, 德语, 意大利语, 意第绪语, 拉丁语, 拉脱维亚语, 挪威语, 捷克语, 斯洛伐克语, 斯洛文尼亚语, 斯瓦希里语, 旁遮普语, 日语, 普什图语, 格鲁吉亚语, 毛利语, 法语, 波兰语, 波斯尼亚语, 波斯语, 泰卢固语, 泰米尔语, 泰语, 海地克里奥尔语, 爱尔兰语, 爱沙尼亚语, 瑞典语, 白俄罗斯语, 科西嘉语, 立陶宛语, 简体中文, 索马里语, 繁体中文, 约鲁巴语, 维吾尔语, 缅甸语, 罗马尼亚语, 老挝语, 自动识别, 芬兰语, 苏格兰盖尔语, 苗语, 英语, 荷兰语, 菲律宾语, 萨摩亚语, 葡萄牙语, 蒙古语, 西班牙语, 豪萨语, 越南语, 阿塞拜疆语, 阿姆哈拉语, 阿尔巴尼亚语, 阿拉伯语, 鞑靼语, 韩语, 马其顿语, 马尔加什语, 马拉地语, 马拉雅拉姆语, 马来语, 马耳他语, 高棉语, 齐切瓦语, 等语言的翻译.

Copyright ©2024 I Love Translation. All reserved.

E-mail: