Jamshoro, Pakistan 2×660MW ultra-supercritical coal-fired power plant project 1 - unit main plant installed by SIMENS production turbine. Turbine part of the high-pressure cylinder and medium-pressure cylinder are a one-way supply, the site does not need to carry out other internal assembly work, directly the overall lifting can be in place. The high-pressure cylinder and the medium-pressure cylinder are arranged vertically on the 15.5 m main operating layer platform between the steam engines. Its vertical center is 14.5m from the A-wall axis, the horizontal center line of the high-pressure cylinder is 5.393m, and the horizontal center of the high-pressure cylinder is 11.163m. High-pressure cylinder weight 128t, medium cylinder weight 180t, the site is to use 630t track crane (84m main arm, 15m over-lifting radius) direct lifting in place medium pressure cylinder and high-pressure cylinder.