Operation pit backfilling. During backfilling of operation pit, for operation pit in stonework section, fine soil shall be used for backfilling first, and the backfilling height shall not be less than 300 mm above the pipe top, then undisturbed soil shall be used for backfilling, and the backfilling shall be more than 300 mm above the surface height. Landscape restoration. The landform of the operation pit shall be restored in time after backfilling. Locate the tag. Mark the parts that have been precisely positioned and repaired, and the way of marking shall be determined by the owner according to his own habits.