G100+500:混凝土挡墙上部建筑垃圾已清理,完成整改;G116:已固化袋装水泥在路边已处理,完成整改。

G100+500:混凝土挡墙上部建筑垃圾已清理,完成整改;G116:已

G100+500:混凝土挡墙上部建筑垃圾已清理,完成整改;G116:已固化袋装水泥在路边已处理,完成整改。" 无。 已对上周提出的G132+200:便道植被绿化不足;建筑垃圾未清理。G132+300:原挖掘机上下便道植被绿化不足,部分建筑垃圾未清理。问题进行了整改。 G110:坡面被冲毁的墙体正在清理,2#挡墙部位存在安全隐患,此部位坡面仍不稳定,已要求进行加护。目前正在按照监理部要求进行加护,要求施工单位加强加固坡面临时围挡,减缓挡墙基础清理,减少坡面的土石流失,采取逐步清理逐步浇筑的方式,并时刻注意坡面变动情况,加强现场安全管理,保证施工安全。降雨期间,严禁坡面任何施工活动。 G424、G529+40:已完全部完工,暂未出现安全问题。 伊江护岸:已完全部完工,暂未出现安全问题。
0/5000
源语言: -
目标语言: -
结果 (英语) 1: [复制]
复制成功!
G100 + 500: an upper wall concrete construction waste has been cleared, to complete the rectification; <br>G116: cured cement bags has been processed at the roadside, to complete the rectification. " <br>None. <br>Has proposed last week of G132 + 200: lack of green vegetation sidewalk; construction waste is not cleaning up .G132 + 300: excavator lack of original vegetation greening up and down the sidewalk, part of the construction waste is not cleaning up the problem of the rectification.. <br>G110: Singapore plane was destroyed wall being cleaned, there are security risks # 2 wall part, this part of the slope remains unstable, has required intensive care. currently under intensive care in accordance with the requirements of the Ministry of supervision, requiring the construction units to strengthen the slope reinforcement temporary enclosure, slowing retaining wall cleaning, reduce the loss of landslides slopes, gradually take to clean up gradually pouring way, and always pay attention to changes in the slope, enhance on-site safety management to ensure construction safety. during the rain, and forbids any construction slope activity. <br>G424, G529 + 40: the Ministry is fully completed, yet security problems. <br>Ayeyawady River revetment: the Ministry has been fully completed, yet safety problems.
正在翻译中..
结果 (英语) 2:[复制]
复制成功!
G100-500: The concrete wall construction waste has been cleaned up, completed rectification; G116: Cured bags of cement have been treated on the roadside, completed rectification. <br>" <br>No. There has been a lack of green vegetation on the G132-200, which was proposed last week, and construction waste has not been cleaned up. G132-300: The original excavator up and down the road vegetation greening is insufficient, some of the construction waste has not been cleaned up. <br>The problem has been corrected. G110: The wall that was washed out of the slope is being cleaned, there is a safety hazard in the blocking wall area, the slope of this area is still unstable, and additional care has been requested. At present, in accordance with the requirements of the Ministry of Supervision to carry out additional care, the construction unit is required to strengthen the reinforced slope face when the fence, slow down the wall foundation clean-up, reduce the slope of the earth and stone loss, take a gradual clean-up and gradual lygination, and always pay attention to slope changes, strengthen site safety management, to ensure construction safety. <br>During rainfall, it is strictly forbidden to carry out any construction activities on the slope. <br>G424, G529-40: Completely completed, no safety issues have occurred. Yijiang bank protection: has been completely completed, there are no security problems.
正在翻译中..
结果 (英语) 3:[复制]
复制成功!
G100 + 500: the construction waste on the upper part of the concrete retaining wall has been cleared and rectified;<br>G116: the cured bagged cement has been treated at the roadside and the rectification has been completed. "<br>No.<br>For g132 + 200 proposed last week, vegetation of access road is insufficient; construction waste is not cleared. G132 + 300: the vegetation on the upper and lower access roads of the original excavator is insufficient, and some construction wastes are not cleared. The problem was rectified.<br>G110: the wall whose slope is destroyed is being cleaned, and there is a potential safety hazard at the 2 × retaining wall. The slope at this part is still unstable, and it has been required to be protected. At present, the reinforcement is being carried out according to the requirements of the supervision department. The construction company is required to strengthen the enclosure when the slope faces, slow down the cleaning of the retaining wall foundation, reduce the loss of earth and stone on the slope, adopt the method of gradual cleaning and pouring, pay attention to the change of the slope at all times, strengthen the site safety management, and ensure the construction safety. During the rainfall, any construction activities on the slope are strictly prohibited.<br>G424, g529 + 40: all completed, no safety problems.<br>Bank revetment of Yijiang River: it has been completed and no safety problems have occurred.<br>
正在翻译中..
 
其它语言
本翻译工具支持: 世界语, 丹麦语, 乌克兰语, 乌兹别克语, 乌尔都语, 亚美尼亚语, 伊博语, 俄语, 保加利亚语, 信德语, 修纳语, 僧伽罗语, 克林贡语, 克罗地亚语, 冰岛语, 加利西亚语, 加泰罗尼亚语, 匈牙利语, 南非祖鲁语, 南非科萨语, 卡纳达语, 卢旺达语, 卢森堡语, 印地语, 印尼巽他语, 印尼爪哇语, 印尼语, 古吉拉特语, 吉尔吉斯语, 哈萨克语, 土库曼语, 土耳其语, 塔吉克语, 塞尔维亚语, 塞索托语, 夏威夷语, 奥利亚语, 威尔士语, 孟加拉语, 宿务语, 尼泊尔语, 巴斯克语, 布尔语(南非荷兰语), 希伯来语, 希腊语, 库尔德语, 弗里西语, 德语, 意大利语, 意第绪语, 拉丁语, 拉脱维亚语, 挪威语, 捷克语, 斯洛伐克语, 斯洛文尼亚语, 斯瓦希里语, 旁遮普语, 日语, 普什图语, 格鲁吉亚语, 毛利语, 法语, 波兰语, 波斯尼亚语, 波斯语, 泰卢固语, 泰米尔语, 泰语, 海地克里奥尔语, 爱尔兰语, 爱沙尼亚语, 瑞典语, 白俄罗斯语, 科西嘉语, 立陶宛语, 简体中文, 索马里语, 繁体中文, 约鲁巴语, 维吾尔语, 缅甸语, 罗马尼亚语, 老挝语, 自动识别, 芬兰语, 苏格兰盖尔语, 苗语, 英语, 荷兰语, 菲律宾语, 萨摩亚语, 葡萄牙语, 蒙古语, 西班牙语, 豪萨语, 越南语, 阿塞拜疆语, 阿姆哈拉语, 阿尔巴尼亚语, 阿拉伯语, 鞑靼语, 韩语, 马其顿语, 马尔加什语, 马拉地语, 马拉雅拉姆语, 马来语, 马耳他语, 高棉语, 齐切瓦语, 等语言的翻译.

Copyright ©2024 I Love Translation. All reserved.

E-mail: