1. Due to the epidemic situation, TTI applied for EMC testing, and on December 10th, one machine with three inductors was sent out first. Three inductances and two inductances need to be tested once each. At the same time, GT also applied to Ningbo Laboratory for EMC testing. 2. On December 11th, the NPQ prototype and safety prototype were sent out. 3. Based on the PP on January 20th and the MP on February 14th, it is necessary to define the material procurement cycle, and determine the completion time of safety regulations and NPQ. 4. Artworks needs to be provided before January 10th. 5. Will sent the quality problems of Sanfeng and the new requirements of EMEA to Guanye.