Set up scaffolding at the row of manhole doors as needed. <br>Disassemble the heat insulation at the manhole door. <br>After the temperature in the continuous expansion vessel decreases, use a wrench to open the manhole door. <br>Set up temporary lighting (36V running lights). <br>Lay wooden boards inside the continuous expansion container as needed. <br>After the lighting and shelf are qualified, the internal inspection of the continuous expansion container will be started. <br>Mechanical damage <br>clean up the debris in the continuous expansion container. <br>Clean the nozzle of the water level gauge, the bottom discharge pipe, and the water inlet pipe. <br>3.18.3.1.2 Weld and wear inspection <br>Check the weld for cracks. <br>Check the wear of each nozzle. <br>After all the work is completed, the person in charge of the work checks the number of staff and the number of tools to ensure that all manhole doors are sealed after they have been evacuated.