Digging drainage ditches and cleaning up barriers between old piles N1 completed a total of 13.95 meters of excavation pile length, N3 completed the completion of the excavation pile length of 13.75 meters, N4 completed the completion of the excavation pile length of 16.0 meters.<br>N2 lock port support mold; N7 lock pad layer watering completed; N8 excavation 2 meters, N10 lock gate pouring completed<br>This week a total of steel pipe pile into a hole 2 holes, steel pipe pile into a total of 2 holes, punching hole 3 to 4m when the water artificial can not play down, drilling into the field for test drilling<br>C20 anti-flushing wall pouring completed, C20 anti-energy pool pouring completed, drainage trench mat pouring completed. C20 retaining wall poured 57m3, a total of 81m3.