开挖排水沟、清理老桩桩间挡板N1累计完成开挖桩长13.95米;N3累计完成开挖桩长13.75米; N4累计完成开挖桩长16.0米。N2锁口支的英语翻译

开挖排水沟、清理老桩桩间挡板N1累计完成开挖桩长13.95米;N3累计

开挖排水沟、清理老桩桩间挡板N1累计完成开挖桩长13.95米;N3累计完成开挖桩长13.75米; N4累计完成开挖桩长16.0米。N2锁口支模;N7锁口垫层浇灌完毕;N8开挖2米,N10锁口浇筑完毕本周共计钢管桩成孔2孔,钢管桩成孔总计2孔,打孔置3~4m的时候出现水人工打不下去,钻孔进场进行试钻C20砼防冲墙浇筑完成,C20砼消能池浇筑完成,排水沟垫层浇筑完成。C20挡墙浇筑57m³,总计81m³。
0/5000
源语言: -
目标语言: -
结果 (英语) 1: [复制]
复制成功!
Excavation of drains, cleaning up old pile baffle between <br>N1 totaled excavation pile length of 13.95 m; N3 totaled excavation pile length of 13.75 m; N4 totaled excavation pile length of 16.0 meters. N2 locking formwork; watering completed cushion locking the N7; N8 excavation of two meters, N10 locking finished pouring <br>week 2 Total steel pile into the hole-hole, a total of 2 steel pile into the hole-hole, punch set 3 ~ 4m occur when water artificial not going to play, diamond drilling approach trial <br>C20 concrete pouring scour wall is completed, the energy dissipation pool C20 concrete pouring is completed, complete gutters pouring cushion. <br>C20 wall pouring 57m³, a total of 81m³.
正在翻译中..
结果 (英语) 2:[复制]
复制成功!
Digging drainage ditches and cleaning up barriers between old piles N1 completed a total of 13.95 meters of excavation pile length, N3 completed the completion of the excavation pile length of 13.75 meters, N4 completed the completion of the excavation pile length of 16.0 meters.<br>N2 lock port support mold; N7 lock pad layer watering completed; N8 excavation 2 meters, N10 lock gate pouring completed<br>This week a total of steel pipe pile into a hole 2 holes, steel pipe pile into a total of 2 holes, punching hole 3 to 4m when the water artificial can not play down, drilling into the field for test drilling<br>C20 anti-flushing wall pouring completed, C20 anti-energy pool pouring completed, drainage trench mat pouring completed. C20 retaining wall poured 57m3, a total of 81m3.
正在翻译中..
结果 (英语) 3:[复制]
复制成功!
Excavation of drainage ditch and cleaning of baffle between old piles<br>The accumulated excavation pile length of N1 is 13.95m; the accumulated excavation pile length of N3 is 13.75m; the accumulated excavation pile length of N4 is 16.0m. N2 locking formwork; N7 locking cushion pouring completed; N8 excavation 2m, N10 locking pouring completed<br>This week, there are 2 holes in total for steel pipe pile, and 2 holes in total for steel pipe pile. When the hole is 3-4m long, the water cannot be manually driven down, and the hole will enter the site for trial drilling.<br>The pouring of C20 concrete anti scour wall, C20 concrete energy dissipation pool and drainage ditch cushion are completed.<br>Pouring of C20 retaining wall is 57m3, totaling 81m3.<br>
正在翻译中..
 
其它语言
本翻译工具支持: 世界语, 丹麦语, 乌克兰语, 乌兹别克语, 乌尔都语, 亚美尼亚语, 伊博语, 俄语, 保加利亚语, 信德语, 修纳语, 僧伽罗语, 克林贡语, 克罗地亚语, 冰岛语, 加利西亚语, 加泰罗尼亚语, 匈牙利语, 南非祖鲁语, 南非科萨语, 卡纳达语, 卢旺达语, 卢森堡语, 印地语, 印尼巽他语, 印尼爪哇语, 印尼语, 古吉拉特语, 吉尔吉斯语, 哈萨克语, 土库曼语, 土耳其语, 塔吉克语, 塞尔维亚语, 塞索托语, 夏威夷语, 奥利亚语, 威尔士语, 孟加拉语, 宿务语, 尼泊尔语, 巴斯克语, 布尔语(南非荷兰语), 希伯来语, 希腊语, 库尔德语, 弗里西语, 德语, 意大利语, 意第绪语, 拉丁语, 拉脱维亚语, 挪威语, 捷克语, 斯洛伐克语, 斯洛文尼亚语, 斯瓦希里语, 旁遮普语, 日语, 普什图语, 格鲁吉亚语, 毛利语, 法语, 波兰语, 波斯尼亚语, 波斯语, 泰卢固语, 泰米尔语, 泰语, 海地克里奥尔语, 爱尔兰语, 爱沙尼亚语, 瑞典语, 白俄罗斯语, 科西嘉语, 立陶宛语, 简体中文, 索马里语, 繁体中文, 约鲁巴语, 维吾尔语, 缅甸语, 罗马尼亚语, 老挝语, 自动识别, 芬兰语, 苏格兰盖尔语, 苗语, 英语, 荷兰语, 菲律宾语, 萨摩亚语, 葡萄牙语, 蒙古语, 西班牙语, 豪萨语, 越南语, 阿塞拜疆语, 阿姆哈拉语, 阿尔巴尼亚语, 阿拉伯语, 鞑靼语, 韩语, 马其顿语, 马尔加什语, 马拉地语, 马拉雅拉姆语, 马来语, 马耳他语, 高棉语, 齐切瓦语, 等语言的翻译.

Copyright ©2024 I Love Translation. All reserved.

E-mail: