When lifting, the tied post should be slowly lifted from the ground by the crane 20CM, and then the sling and crane stability should be checked. The steel column should be raised to 40-100mm away from the safety surface, the installer will be responsible for assisting the lifting of the steel column, and aimed at the foot of the column for anchoring, command crane drop, insert the column into the anchor, and then tighten the anchor. The sling is slowly released after the steel column has been initially corrected.