5.1.控制、测量、保护、信号回路检查和绝缘试验。5.1.1.按设计要求检查控制、测量、保护信号回路,电缆校对应准确无误,接线端子紧固,机械的英语翻译

5.1.控制、测量、保护、信号回路检查和绝缘试验。5.1.1.按设计要

5.1.控制、测量、保护、信号回路检查和绝缘试验。5.1.1.按设计要求检查控制、测量、保护信号回路,电缆校对应准确无误,接线端子紧固,机械部分检查良好。5.1.2.绝缘及耐压试验使用500V兆欧表测量,其绝缘电阻值应大于1MΩ,对地工频1000V耐压试验只对控制回路进行,持续时间1分钟;当回路绝缘电阻大于10MΩ时,可用2500V兆欧表代替,持续时间1分钟,柴油机控制盘24V控制回路不应进行耐压试验。 5.2.装置单体元件调整、整定试验柴油机智能控制器内部的相应控制和保护参数的设定由柴油机厂家进行设定,并提供给电厂进行确认后才能投入使用。 5.3.柴油发电机组一次设备交接试验5.3.1.发电机试验;5.3.2.测量定子绕组的绝缘电阻;5.3.3.测量定子绕组的直流电阻;5.3.4.定子绕组交流耐压试验;5.3.5.测量相序,电机出线端子标号应与相序一致;5.3.6.柴油发电机出口母线绝缘试验。
0/5000
源语言: -
目标语言: -
结果 (英语) 1: [复制]
复制成功!
5.1. Control, measurement, protection, signal circuit inspection and insulation test. <br>5.1.1. Check the control, measurement, and protection signal circuits according to the design requirements, the cable calibration is accurate, the wiring terminals are tight, and the mechanical parts are well checked. <br>5.1.2. The insulation and withstand voltage test is <br>measured with a 500V megohmmeter, and the insulation resistance value should be greater than 1MΩ. The ground power frequency 1000V withstand voltage test is only performed on the control circuit, and the duration is 1 minute; when the circuit insulation resistance is greater than 10MΩ , It can be replaced by a 2500V megohmmeter. The duration is 1 minute. The 24V control circuit of the diesel engine control panel should not be subjected to a pressure test. <br>5.2. Device single component adjustment and setting test <br>The corresponding control and protection parameters of the diesel engine intelligent controller are set by the diesel engine manufacturer and provided to the power plant for confirmation before it can be put into use. <br>5.3. Diesel generator set primary equipment handover test <br>5.3.1. Generator test; <br>5.3.2. Measuring the insulation resistance of the stator winding; <br>5.3.3. Measuring the DC resistance of the <br>stator winding ; 5.3.4. Stator winding AC withstand voltage test; <br>5.3.5. Measure the phase sequence, the motor outlet terminal label should be consistent with the phase sequence; <br>5.3.6. Diesel generator outlet bus insulation test.
正在翻译中..
结果 (英语) 2:[复制]
复制成功!
5.1. Control, measurement, protection, signal circuit inspection and insulation tests.<br>5.1.1. According to the design requirements to check the control, measurement, protection signal circuit, cable correction corresponding to accurate, terminal fastening, mechanical part of the inspection is good.<br>5.1.2. Insulation and pressure resistance tests.<br>Using the 500V MO meter measurement, its insulation resistance value should be greater than 1Mω, the ground frequency 1000V pressure resistance test is only carried out on the control circuit, the duration of 1 minute; <br>5.2. Device unit component adjustment, adjustment test.<br>The setting of the corresponding control and protection parameters within the diesel engine intelligent controller is set by the diesel engine manufacturer and provided to the power plant for confirmation before it can be put into use. <br>5.3. Diesel generator set a equipment handover test.<br>5.3.1. Generator test;<br>5.3.2. Measuring the insulation resistance of the sernut windings;<br>5.3.3. Measuring the DC resistance of the synth winding;<br>5.3.4. Senth winding AC pressure test;<br>5.3.5. Measure phase sequence, motor terminal label should be consistent with phase sequence;<br>5.3.6. Diesel generator outlet bus insulation test.
正在翻译中..
结果 (英语) 3:[复制]
复制成功!
5.1. Control, measurement, protection, signal circuit inspection and insulation test.<br>5.1.1. Check the control, measurement and protection signal circuits according to the design requirements, ensure that the cable alignment is correct, the wiring terminals are tight, and the mechanical part is in good condition.<br>5.1.2. Insulation and withstand voltage test<br>When 500V megger is used to measure, the insulation resistance value should be greater than 1m Ω. The 1000V withstand voltage test to ground power frequency is only conducted for control circuit, lasting for 1 minute; when the insulation resistance of circuit is greater than 10m Ω, 2500V megger can be used to replace it, lasting for 1 minute. The withstand voltage test should not be conducted on the 24 V control circuit of diesel engine control panel.<br>5.2. Single component adjustment and setting test<br>The internal control and protection parameters of the intelligent controller of diesel engine are set by the diesel engine manufacturer and provided to the power plant for confirmation before being put into use.<br>5.3. Primary equipment handover test of diesel generator set<br>5.3.1. Generator test;<br>5.3.2. Measure the insulation resistance of stator winding;<br>5.3.3. Measure the DC resistance of stator winding;<br>5.3.4. AC voltage withstand test of stator winding;<br>5.3.5 measure the phase sequence, and the label of motor outlet terminal shall be consistent with the phase sequence;<br>5.3.6. Insulation test of diesel generator outlet bus.<br>
正在翻译中..
 
其它语言
本翻译工具支持: 世界语, 丹麦语, 乌克兰语, 乌兹别克语, 乌尔都语, 亚美尼亚语, 伊博语, 俄语, 保加利亚语, 信德语, 修纳语, 僧伽罗语, 克林贡语, 克罗地亚语, 冰岛语, 加利西亚语, 加泰罗尼亚语, 匈牙利语, 南非祖鲁语, 南非科萨语, 卡纳达语, 卢旺达语, 卢森堡语, 印地语, 印尼巽他语, 印尼爪哇语, 印尼语, 古吉拉特语, 吉尔吉斯语, 哈萨克语, 土库曼语, 土耳其语, 塔吉克语, 塞尔维亚语, 塞索托语, 夏威夷语, 奥利亚语, 威尔士语, 孟加拉语, 宿务语, 尼泊尔语, 巴斯克语, 布尔语(南非荷兰语), 希伯来语, 希腊语, 库尔德语, 弗里西语, 德语, 意大利语, 意第绪语, 拉丁语, 拉脱维亚语, 挪威语, 捷克语, 斯洛伐克语, 斯洛文尼亚语, 斯瓦希里语, 旁遮普语, 日语, 普什图语, 格鲁吉亚语, 毛利语, 法语, 波兰语, 波斯尼亚语, 波斯语, 泰卢固语, 泰米尔语, 泰语, 海地克里奥尔语, 爱尔兰语, 爱沙尼亚语, 瑞典语, 白俄罗斯语, 科西嘉语, 立陶宛语, 简体中文, 索马里语, 繁体中文, 约鲁巴语, 维吾尔语, 缅甸语, 罗马尼亚语, 老挝语, 自动识别, 芬兰语, 苏格兰盖尔语, 苗语, 英语, 荷兰语, 菲律宾语, 萨摩亚语, 葡萄牙语, 蒙古语, 西班牙语, 豪萨语, 越南语, 阿塞拜疆语, 阿姆哈拉语, 阿尔巴尼亚语, 阿拉伯语, 鞑靼语, 韩语, 马其顿语, 马尔加什语, 马拉地语, 马拉雅拉姆语, 马来语, 马耳他语, 高棉语, 齐切瓦语, 等语言的翻译.

Copyright ©2024 I Love Translation. All reserved.

E-mail: