After the installation of the pipe flange of the secondary coupling alignment and the opposite of the pump flange, the pipe stress test work should be carried out. First, the two percentage tables are mounted on the motor shaft by magnetic table seat adsorption, the needle points to the joint shaft on the pump side into two vertical faces, one axial, one radial, the index of the percentage table zero, and then the pipe flange and Pump flanges are bolted, bolted are continuously completed, the flange bolts are initially tightened at 10% of the total torque value, again tightened to 30% of the total torque, and finally 100% of the total torque (pipe bolt torque value is specified or designed by the equipment manufacturer).