According to Article 6-d main contract: liquidated damages. Extension of the completion date, contract duration completion date or approved in accordance with Article 20.1 of General Conditions of Contract for each delayed one day 0.1% work corresponding to the contract value of the portion of the bond for construction in progress or completed after the extension period, according to the General Conditions of Contract section 34.4 (b) of Article, unfinished projects or delayed after the deadline to complete the largest part of the work of the liquidated damages in the amount of 10% of the final contract price ,. as well as the completion date specified in the special Terms and Conditions GCC2.1 delay; because of the design, procurement, construction unit Operating lag lag caused by the project completion date, which led to the owners in accordance with our contract, liquidated damages penalties proposed against us, how to prevent and respond to liquidated damages our cause of non-owners