In order to guide the construction personnel to carry out correct construction and ensure safe production and civilized construction, the construction scheme is specially prepared. This construction scheme is applicable to the thermal control system of C2 bid section of Vietnam coastal phase II 2 × 660MW coal fired power station projectThe ground debugging work mainly includes meter calibration, local equipment debugging, loop debugging, thermal control power supply system, etc.